November 16, (THEWILL) – Nigeria’s reported crude oil recovery has raised expectations for the petroleum sector. But sustaining the gains and achieving the Federal Government’s two-million-barrel-per-day target will depend on reliable infrastructure, improved asset performance and investment translating into consistent output.
Nigerian National Petroleum Company Limited (NNPC) Group Chief Executive, Bashir Ojulari, announced on November 3, 2026, at the Abu Dhabi International Petroleum Exhibition and Conference (ADIPEC), that reforms had added 600,000 barrels per day to national production, lifting output from about 1.2 million to 1.8 million barrels per day.
Ojulari attributed the increase to the Petroleum Industry Act, an improved investment climate, better investment decisions and closer collaboration with industry partners. He said NNPC was targeting two million barrels per day by 2027 through infrastructure maintenance, protecting existing production, raising output from producing assets and advancing new projects.
NNPC did not specify the period over which production rose by 600,000 barrels per day, making comparison with the regulator’s figures important.
The Nigerian Upstream Petroleum Regulatory Commission (NUPRC) reported that crude oil production, excluding condensates, averaged 1.53 million barrels per day in September. Combined crude and condensate production averaged 1.717 million barrels per day, up 2.34 percent from August.
Daily output peaked at 1.84 million barrels per day, a single-day high. Condensates are excluded from the crude volume used to assess OPEC quota compliance.
September crude output was 102 percent of Nigeria’s 1.5 million-barrel-per-day quota, the fifth consecutive month the country met or exceeded its quota. NUPRC attributed the performance to stable asset operations and the absence of major pipeline outages.
However, cumulative figures show the recovery remains fragile. Nigeria produced 450.17 million barrels of crude and condensate between January and September 2026, against 457.65 million barrels in the same period of 2025. The 1.63 percent decline means September’s improvement had not reversed the year-on-year contraction.
Pipeline reliability remains central. NUPRC’s 2025 annual report put average deferred crude and condensate production from outages, leaks and shut-ins at 116,563 barrels per day. Damaged export pipelines were among the main constraints. The regulator cautioned that its production and deferral figures were unreconciled and should not be treated as export volumes.
NUPRC also recorded 357 oil spills in 2025, 177 attributed to sabotage, and 3.33 million barrels of reconciled crude theft, including 2.19 million barrels in the fourth quarter. These incidents and evacuation failures undermine output.
There is a sizeable pool of potential output to restore. In October, NUPRC said more than 788,000 barrels per day of shut-in production had been identified across 63 operators. By November 10, it had approved 595 well re-entries, 145 new drilling operations and 39 field development plans in 2026. These approvals do not represent completed wells or production already added. It reported 100 rigs, 46 active.
READ ALSO:
NUPRC’s 2026 licensing round offers 40 blocks, while 22 offshore projects expected between 2026 and 2030 could attract $30 billion to $50 billion. The regulator says deep offshore incentives could unlock up to $50 billion and eventually support another one million barrels per day. These are projections, not committed production.
Investment execution will be as important as attracting capital. NUPRC said multi-client seismic companies invested more than $100 million in seismic data acquisition in Nigeria in the three years after the PIA’s enactment. NNPC said commercial agreements covering about $20 billion had been concluded, citing TotalEnergies’ Ubeta, Shell’s Bonga South-West/Aparo and Eni’s Zabazaba-Etan. The figure is not proof that the full amount has been spent or that the projects are producing.
Bonga South-West/Aparo illustrates the long lead time. In August, NNPC and its partners signed amendments to the production-sharing contract and dispute settlement agreement, advancing the project towards a final investment decision. Pre-front-end engineering design had been completed, with front-end engineering to follow. The project is expected to attract $15 billion to $21 billion over its lifetime and reach peak production of about 175,000 barrels of oil per day, alongside 140 million standard cubic feet of gas daily. It is not yet producing.
Ubeta is a gas and condensate development, not a major crude oil project. TotalEnergies and NNPC took the final investment decision in June 2024. The six-well development is expected to start in 2027, producing 300 million cubic feet of gas daily, equivalent to about 70,000 barrels of oil equivalent per day.
Zabazaba-Etan could add approximately 150,000 barrels per day, according to NNPC. However, settlement of the OPL 245 dispute in March 2026 cleared the way for development; it did not mean a final investment decision or immediate production.
To reach two million barrels per day, Nigeria needs about 200,000 additional barrels based on NNPC’s announced 1.8-million-barrel baseline. Against September’s NUPRC crude-only average of 1.53 million barrels, the gap is larger. The figures should not be conflated.
The Petroleum Industry Act and fiscal changes may improve project economics, but investors will still weigh regulatory consistency, security and evacuation infrastructure. The test is sustained output, fewer shut-ins and projects reaching final investment decisions and first oil.
Ogochukwu Onwaeze is a writer specializing in business and economic journalism. At THEWILL News Media, she translates market trends, financial developments, and policy shifts into clear and engaging stories.